Project
scope

The Request For Proposal presented by the CPP Infrastructure entails the replacement of the San Elijo Lagoon bridge, construction of the HOV lanes & walls on I-5 NCC Phase 1, Stage 1. Our project uses the Design-Build process. Optima Group demonstrates expertise in program development level functions through project design, procurement, construction administration, and commissioning. We offer full engineering services, including design and construction, and staying under the owner's budget ($200,000,000).

Proposed Cost: $187M
Start Date: January 2021
Completion Date: February 2023
Project Status: Ongoing

Our promises embody what we do and what we stand for because we design with community in mind. Optima offers clients the accessibility and support of a local firm with the stability and resources of a multi-national organization. Optima is happy to announce our firm's lump sum proposal of $ 187M for the I-5 North Coast Corridor San Elijo Lagoon - Phase 1.